2019 Bond Election Engineering Report
Bond Construction and Cost – Feb. 22, 2016
Bond Construction and Cost Progress – March 11, 2016
There is 30% of the original scope still to be completed for the sanitary sewer. Its probable construction cost is $218,000.00. This work will be completed with the first bid job that the district has. It will probably be bid with the CDBG Waterline project along Kipp Avenue.
G.C.W.C. & I.D. No. 12 Bond Projects Graph March 2016
Download: G.C.W.C. & I.D. No. 12 Bond Projects Graph 2016-02-22
March Bond Construction Costs
The March Bond Construction costs for both engineering and construction have been posted.